Current Filter: CAD>>>>>Case Study> The BIM factor Editorial Type: Case Study Date: 11-2015 Views: 3017 Key Topics: CAD BIM Construction Process Plant Key Companies: Autodesk Atkins Galliford Try Costain Key Products: AutoCAD Plant 3D Navisworks Key Industries: Health | |||
| BIM was used extensively during the design of the new Waste Water Treatment Plant in Liverpool by Galliford Try Costain and Atkins A joint venture partnership of Galliford Try Costain and Atkins (GCA JV) is currently completing work on a £150 million expansion of the Liverpool Wastewater Treatment Works. The joint venture was specifically set up to deliver detail design and construction for United Utilities Asset Management Programmes, and has been in partnership with the company for over 12 years. The completed Liverpool program will provide the works with the capacity to deal with 960 megalitres per day, serving the needs of more than 600,000 people. Rather than rely on the traditional 2D workflows for detail design of this flagship project, the GCA JV Board of Directors recognised that the delivery of the project could be greatly enhanced by employing Building Information Modelling (BIM). As civil and structural detail designers for the project, Atkins, one of the world's largest engineering consultancies, with more than 100 offices in the United Kingdom, was charged with leading the implementation of the BIM strategy. According to Paul Heath, BIM lead adopter for Atkins Water Operations, BIM has proved to be a time- and cost-saving asset on the project: "A BIM process is built around 3D models, and helps the whole team to better understand the project before and during construction. Large, complex projects progress with fewer issues when you use BIM. There were numerous instances of problems avoided and value engineering opportunities recognised early in the design stages, which greatly contributed to cost savings."
THE NEW WAY OF WORKING
THE CHALLENGE A number of complexities stood out on the project. The new plant is located in an existing operational dock, which is subject to a preservation order by English Heritage. This meant that the design had to avoid damage to the walls. The dock was also still operational, so the gates had to be closed and a permanent closure constructed prior to dewatering, sand infilling, and piling. "A facility of this type and size would typically occupy a huge swath of land," says Heath. "You expect acres of space to work with, but on this project the footprint is very confined. The solution was to go up rather than out, so there are eight treatment cells over another eight treatment cells. We thought that designing in 3D could help us manage all that complexity, and that using Autodesk Navisworks Manage software could help us coordinate all the models required by the project."
THE SOLUTION The 2D drawings were then sent to the Global Design Centre in India for reinforcement detailing. The speed demonstrated in this 'new' workflow helped to quickly allay any concerns that designing in 3D would slow down the production of the 2D construction drawing deliverables. Matt Lees, for Atkins, explained further. "We designed in 3D from the outset, and then generated 2D drawings from the models," he says. "Those who were hesitant saw that you can easily create a 2D drawing from the 3D model if you need one. People realised they could get the advantages of 3D without a downside. "Interestingly, we did have a few project participants who chose to use 2D workflows against our advice or requirements," adds Heath. "It's been a relatively issue-free project, but those 2D-based processes have been a large part of the few issues that we have encountered."
A COORDINATION HUB